District: Construction Project


Story image 1_0
Successful first day - Sept. 8. Students loading buses at the end of the day.

Construction - September 7 - 11

September 11, 2009

Most of the work being done this week was in the Early Childhood Center classrooms, hallway, and the south entrance.  Hopefully this area should be completed in another week or two making it possible for the ECFE staff to move in to their new classrooms.

Crews should begin paving the south parking lot  in the next few days as work on the district offices, science rooms and areas on the north side of the building continues.

 