Construction Update - March 2010
This slide show includes pictures of the work being done in the cafeteria, kitchen, high school office and photos of the completed remodel of the district office, elementary office, and the new science rooms. read more
Construction Update Dec. 31, 2009
Construction continues in the district offices, science rooms, high school offices and cafeteria. read more
Construction - December
Progress has slowed somewhat, but then portions of the building project weren't to be completed until the summer of 2010. We were able to snap just a few of the projects that have become accessible: District offices and science . . . read more
Construction - October
Construction on the building continues, but at a much slower pace these days as these next phases aren't scheduled to be completed until next summer. Work however, will continue on the inside so watch for updates as they become available. read more
Construction - September 28 to October 2
Construction progress seems to have slowed a bit, but each day one can still see additions here and there. read more
Construction - September 7 - 11
Most of the work being done this week was in the Early Childhood Center classrooms, hallway, and the south entrance. Hopefully this area should be completed in another week or two making it possible for the ECFE staff to move in to . . . read more
Construction - August 31 to Sept 4
This week saw a bit more progress, especially on the south side of the building. Curb and gutter went in as did a couple of sidewalks. Windows and doors were installed on the new south entrance and the terrazzo floor received a . . . read more
Construction - August 23 - 27
This week saw a bit of progress. Brick work on the east side of the building was completed and the scaffolding came down. Roofers began work on areas over the cafeteria prep area and the district offices. The parking lot . . . read more
Construction - August 17 - 20
Construction Week - August 17 to August 20 This week construction crews began work on the north side of the school, putting up walls for the high school office, fine arts entrance, and the old Headstart room. Structural steel beams . . . read more
Construction - August 10-13
Week of August 10 - 13 Construction Photos read more
Construction - August 3 - 6
Construction slide show for the week of August 3 - 6. read more
Construction - July 24 - 30
Here's this week's slide show of the construction project. Remember, once you click on the picture in this article, an icon appears in the bottom right-hand corner. Click that and then play to view slide show. read more
School Construction Project - 2009
Demolition is complete and construction is now underway in preparation for the new additions and improvements to the Osakis School. Pictures of the building progress will be posted at the link listed below and we'll post those . . . read more